Our team participated in a project for a renovation of the existing CFB boiler building in a power plant near the west coast of Europe. The task was to build the 3D BIM model of the existing steel structures, based on the old archived drawings. Of course, we didn’t have all the documentation on hand and taking into account the coming deadlines, the challenge was exactly for us.

The goal of this model is to be used from the mechanical and layout engineers in order to avoid clashes and to improve the arrangement of the equipment.

The new steelwork is c.a. 450 tonnes.

The main dimensions of the site layout plan are 44,20m and 28,20m. The total high is 59,50m.

Project parameters

BIM model
Steel detailing
Bill of quantities
Design duration
2 month

  • Client: Confidential